Saving Trillions in the Energy Transition

On its current course, the energy transition is unaffordable and will lead to unreliable and fragile grids. And that’s in a grid the size of the UK’s or France’s, and would be proportional to the size of the grid and the economy. Storelectric can change all that. To get started and save the first tens or hundreds of billions per grid, all that’s needed is to build plants and integrated developments. But to save the big money, regulatory systems and grid management need to change substantially world-wide.

Grid Reinforcement for Renewables

Jeremy Warner of the Daily Telegraphs writes, drawing conclusions from statements from National Grid, that to convert the electricity grid from its current profile to 100% renewables will require a grid five times its current size. This is totally un-feasible.

Today’s grid has 76.6GW generation. As it’s close to saturation, call it (generously, for this analysis) an 80GW grid. Quintupling it means adding a further 320GW grid capacity. But figures worked out from an Ofgem announcement late December 2022 show that each GW of new grid capacity costs £3bn approximately, rising exponentially. That means £960bn, a shade under a trillion pounds.

And grid capacity has operational, maintenance (O&M) and finance costs to. In the same article, National Grid’s official O&M costs are 5% of capital costs plus another 5% for financing and amortisation. That means additional costs rising to £96m per annum, taking it way beyond the trillion pounds.

Much, possibly most, of this reinforcement can be avoided by connecting renewables to the grid through Storelectric’s CAES, which is the world’s most efficient and cost-effective widely implementable long duration energy storage (LDES).

System Operational Costs

Those O&M costs are for the hardware of the grid itself: the wires, substations etc. System Operation is about procuring the:

  • Power quality services that grids’, service providers’ and consumers’ equipment needs to operate smoothly, efficiently and with minimum wear-and-tear;
  • Balancing services for intermittency;
  • Stability services to prevent faults cascading and multiplying through the grid as they did on August 19th 2019;
  • Ancillary services to recover from problems; and
  • Restoration and Black Start services in case of even greater problems.

Last year I looked at those system operation costs: they were £8bn p.a. more in 2021-22 than just three years before, with every element increasing exponentially. There is no way of foreseeing where this exponential price escalation will end; no modeller was able to predict it thus far. Given that the £8bn cost increase came from increasing renewables from 16% of all electricity to 38% (see p30 here), a floor of £50bn p.a. would not be an unreasonable guesstimate.

The principal reason for this is a reliance on batteries and other small-scale services such as Demand Side Regulation (DSR), almost none of which is naturally inertial, to provide such services – and to provide them in locations that are remote from the renewable generation that they support. Some of the services are inferior when produced by DC systems even with grid-forming inverters, and some (like Black Start) are impossible. Were the systems providing such services to be naturally inertial, then These services would be provided cheaply, easily and much more manageably.

Think back to the grid before 2010. It was powered by naturally inertial power stations. Because of that natural inertia, ultra-fast response times were not needed. Millions of micro-contracts for small-scale services were unnecessary. Grid control and operation was relatively simple, efficient and cheap. The whole lot cost billions less per annum, and was much more stable, reliable and resilient than today’s grid.

Any renewables connected through suitable-scale (size and duration) LDES can be treated as though it were an old-fashioned power station providing dispatchable (variable on demand) electricity with all the requisite power quality, balancing, stability, ancillary, restoration and recovery services.

The Hydrogen Economy

All the above is about powering the electricity grid. Additional costs will be incurred to support a clean hydrogen economy.

Clean hydrogen, in all its forms (electrolysis, SMR + CCS etc.) needs large amounts of electricity. So do all the related industries, e.g. nitrogen fixing, ammonia synthesis, methanol synthesis, iron and steel. Even if the hydrogen economy is only half the size of the expanded electrically-powered economy (as I suggested in a previous blog), that’s another 250% of today’s grid, i.e. 200GW @£3bn/GW = £600bn capital costs, £60bn p.a. network operation costs and at least another £25bn p.a. system operation costs.

This can be reduced by a third or so by sufficient LDES in the system. If the LDES is between the renewables and the hydrogen economy industries, that mitigation can increase to between half and two-thirds. If Storelectric’s integrated solutions, combined with the company’s Green CAES™, were implemented such that a majority of the hydrogen economy were to be powered by renewables in “island grids” (i.e. off the national electricity grid), then most of this additional cost can be eliminated.

The potential Savings

So the total electricity system network and system costs of the energy transition, without Storelectric’s proposals, is over £1.5 trillion capital costs and £225 billion per annum ongoing costs, for the UK alone. This is unaffordable and impractical, and even so it yields a much weaker and more fragile energy system.

With full implementation of Storelectric’s proposals, these costs can be reduced by between two-thirds and three-quarters, and provide for a much more affordable, reliable and resilient energy system.

And the UK is only 0.7% of the world’s population, not much more than 1% of its energy consumption. Therefore, world-wide, the potential costs and benefits must be multiplied by 100-140 times.

Achieving the Savings

However to achieve the fullness of these savings requires some strong and decisive actions by the government, regulator and grid, including:

  1. Adapt the regulatory and contracting system to incentivise it at no extra cost (indeed, major cost savings) to consumers or taxpayers;
  2. Incentivise first-of-a-kind plants and arrangements, for all technologies that can operate commercially without subsidy, with up-front contracts for the full revenue stack, with a lead time suitable for its needs – again, at no cost to consumers or taxpayers;
  3. Optionally, if the country wishes to encourage more new technologies, public funding schemes may be added to the above two measures – noting that if the first two are also applied, the amount of public funding will greatly reduce.

The best and fairest way to pay for all of this, which would be revenue positive for governments, avoid penalising domestic growth and maximise incentives for the energy transition, is an Emissions Added Tax. It would also provide a surplus to mitigate the needs of those who lose out in the energy transition, especially the poor who, in turn, should be assisted directly and not by reducing their energy costs as that would blunt incentives.